Government
Back
 Category: New Parking Structure Projects Industry: Government Location: Fairmont, WV
Project Owner: City of Fairmont, WV, Jay Rogers (304) 367-0490
Architect: Omni Associates, Steve Barnum (304) 367-1417
Value: $3,500,000
Start Date: Summer 2005
Date of Completion: Spring 2006
Engineer: Stroud, Pence & Associates, Ed Pence
CWC Contract: $3,500,000
% of Cost of Work Performed With CWC Forces: 10%
Project Description: The project is a 3-level (grade plus 2 supported levels), pre-cast concrete parking structure which provides 225 parking spaces. The project has approximately 50,000 sq. ft. of structural area and an additional 20,000 sq. ft. of area on grade for a total area of approximately 70,000 sq. ft. The project entailed extensive use of thin-set brick panels and expansive glass in the main stair/elevator enclosure as its primary architectural features.
|